1

Construction of Qarachug road 27.4 km 

EBL Governorate

12months 

Makhmur

7,250,000

2021-2022

2

Land scaping earth work Pavilion compound 

LALAV group

12months 

Erbil

3,000,000

2021-2022

3

Construction of EBL-DHK Highway road 16km 

Hemin group

12months 

Erbil

12,000,000

2020-2021

4

Construction of EBL 120m Highway road

Hemin group

24months 

Erbil

8,000,000

2019-2020

5

Supply of PPE (Mask, gloves, hand gel) kit 

Acted 

12months

Mosul

12,242

Jul-21

6

Supply and installation of Oxygen plant 15m3/hr baiji general hospiatl

IOM

120 days

Tikrit

62,926

Jul-21

7

Renovation of Baharka Park

UNHCR

90days

Erbil

56,448

Feb.2021

8

Construction of Aram Village compound consist of 700 houses

Investment

2 years

Erbil

2021

9

Remodeling of Children Physio department in Dohuk

GIZ-AISPO

60days

Dohuk

39,000

Dec.2020

10

Remodeling of Zanin Health Center in Dohuk

GIZ-AISPO

90days

Dohuk

231,000

Dec.2020

11

Disludging of Cesspool of Salamiyah camp

ACTED

6 months

Salamiyah

Jan-20

12

Supply of tools and Chemical materials

ACTED

3 days

Dohuk

3,316

Dec.2019

13

Supply of Kit Tools

PAH

one day

Erbil

1,718

Dec.2019

14

Rehabilitaion of two schools in Sinjar Nineve

WVI

40 days

Nineve

20,000

Dec.2019

15

Rehabilitation for Al Shaab Park Ninawa - Mosul

ACF

10 days

Mosul

49,880

Dec.2019

16

Construction of water network, Hydrant and Fire Fighting system of Dohuk Termanl

Dareen Group

3months

Dohuk

920,000

Oct.2019

17

Renovation of Shelters in Tallafr Mosul

ACTED

60days

Mosul

25,000

Sep-19

18

Several works of cesspool construction and cabin works

ACTED

7 days

Salamiyah

4,000

2018

19

Supply HDPE pipes and fittings

ACTED

2 days

Mosul

5,000

2018

20

Variant and extend supply of (UPS + Acrylic cabinet + constructoin works) of Zakho

AISPO

30 days

Dohuk -

50,000

2018

21

Health Laboratory

Zakho

22

Supply of NFI + wash materials (HDPE pipes and fittings)

ACTED

2 dyas

Mosul -

5,400

2018

23

Construction of Zakho Health Laboratory

AISPO

6 months

Dohuk

310,000

2018

24

Supply of Construction materials

ACTED

7days

Mosul

85,000

2017

25

Supply of Furniture, Caravan and NFI goods to Salamiyah camp

ACTED

7 days

Mosul

15,000

2017

26

Implementation of Kurd Max Satellite canal Building

KURD MAX

12 months

Erbil

745,000

2017

27

Renovation and Extension of Nawroz private hospital

Nawroz Hospital

10 months

Erbil

781,064

2017

28

Supply of Winter Kits

IRC

one year

Baghdad,

Frame Work

2016-2017-2018

29

Supply of Hygiene and Underwear kits

IRC

0ne year

Tik it S lBaghdad,

Frame Work

2016 -2017-2018

30

Transportation and distribution of fuel for schools in Erbil

M.O.Education

20 days

Erbil

112,000

2016

31

kid zone park include pump station construction

Rwanga

6months

Dohuk

478,000

2015-2016

32

Rehabilitation Supply

ACTED

1day

Erbil

13,000

Nov.2016

33

Supply of Cleaning kits

ACTED

1day

Erbil

2,000

Nov.2016

34

Supply of Cleaning kits

ACTED

1day

Erbil

6,000

Oct.2016

35

Supply for Biscuits

ACTED

2days

ERB, DHK

10,000

Aug.2016

36

Supply of School Kits

ACTED

4days

ERB, DHK

14,500

Aug.2016

37

Supply of Cleaning Kits

ACTED

2days

ERB

2,000

Aug.2016

38

Supply of Military uniforms consist of 10 items (uniform, jacket, beret, belt, logos, t shirt,

Interior Ministry

60days

Erbil

1,152,000

2016

39

Construction and Establishment of a Farm of 75000m2 include construction of ( 6
 houses, 2 swimming pools, road, fence, electric net with water net…etc.)

Private Investment

12months

Erbil

2,000,000

2015

40

Supply and installation of 48 Green house with dimension (51m*10m*3.25m) the work
 include G.I. tanks, irrigation system and pipes with all accessories.

Private Investment

30days

Garmian
 Area

424,000

2015

41

Construction of Qadiya IDP 2000 caravans Camp the work include (, kindergarten, youth center by prefab fabrication) include Bore hole drilling 2 no, main pipe line and pump

Rwanga

60days

Dohuk-

14,000,000

2015

42

Construction of Khanaqeen IDP 512 tents Camp (300m*600m) include pump station with main pipe line.

ACTED

56days

Khanaqeen

1,200,000

2014-2015

43

Land scaping, grading and Supply laying of Gravel of 5-7 cm thick with leveling

ACTED, NRC

2days

Erbil -

6000$

2014

44

45

Construction of CFS/ YFS and CPU (Kindergarten)

ACTED

30days

Dohuk -

83,000

2014

46

47

Supply of Fire extinguisher different types, fire blanket safety tools

Al shimal oil Co.

30days

Sulaimany

452,000

2014

48

Construction of 6m Cesspool, slab construction, latrines connection and latrines fencing.Garmawa camp

ACF

20days

Erbil

40,000

2014

49

Supply of (prefab cabins, benches, shadow nets and construction of walk ways...etc.)

ACTED

2months

Erbil

20,000

2014

50

Supply of Family mall by cleaning Hygiene materials Diversy brand

Family mall

12months

Erbil

On going

2015-2017

51

Supply of Family mall by cleaning machines and equipment’s TASKI brand

Family mall

12months

Erbil

On going

2015-2017

52

Construction of 4 hangers the work include construction of cesspools and septic tanks

M.O. Peshmarga

6 months

Erbil -

1,250,000

2013 -2014

53

Construction of water network of Syrian refugee Gawilan camp include Bore hole work with pump station

ACF

45 days

Dohuk - Gawilan

350,000

2014

54

Construction of (Septic tanks, cesspool, sanitary connection, Sanitary concrete slabs,etc) for Syrian refugee Gawilan camp

ACF

2 months

Dohuk - Gawilan

40,000

2014

55

Construction of Qushtapa youth center project

Rwanga

3 months

Erbil

250,000

2014

56

kindergarten camp of Dara Shakran project

Rwanga

3months

Erbil

225,035

2014

57

Construction of work shop area of Prefab Design and construction 4000m2

M.O. Peshmarga

2months

Erbil -

650,000

2013

58

Supply of 200 Prefab cabins 3*6

M.O. Peshmarga

2 months

Erbil -

900,000

2013

59

Supply of 200 tents (4m*6m)

M.O. Peshmarga

1 months

Erbil -

120,000

2014

60

Construction of 2 sleeping halls building the work include construction of cesspools and

M.O. Peshmarga

8 months

Erbil -

750,000

2013

61

septic tanks and pump station.

Baharka

62

Construction of 2 restaurant the work include construction of cesspools and septic tanks and pump station

M.O. Peshmarga

6 months

Erbil - Baharka

250,000

2013

63

Construction of Ganjan city water and sanitary network the work include construction of cesspools and septic tanks

Municipality Erbil

6 months

Erbil -

350,000

2012

64

Supply and installation of 34m3 galvanized water tank to Kirkuk children hospital with net connection and pump station

Ministry of Health

2 months

Kirkuk

123,000

2011

65

Procurements, Camp construction, Accommodation, Machine supply, HR, Survey and Profile checking, Construction fabrication installation for project of High Way Dokan Chiwar Qurna second part

USAS

2 months

Sulaimany

1,250,000

20011-2013

66

Procurements, Camp construction, Accommodation, Machine supply, HR, Survey and Profile checking, Construction fabrication installation for project of High Way Erbil Koya second part Investment agency Naqar CHAR BRA, CHAR DERIA & 4b group

USAS

2 months

Erbil

1,750,000

20011-2013

67

Landfill cutting and filling for Kurdistan city Erbil

NAQAR

4 months

Erbil

600,000

2012

68

Implementation of Soran Private Hospital

Zozik

12months

Erbil

2,500,000

2010

69

Implementation of Soran MRI complex

Zozik

12months

Erbil

2,786,000

2010

70

Koya hay bat sultan man street

M.O. Rehabilitation

3 Years

Koya

5,382,042

2010-2013

71

Digging of five water wells in Garmian with construction of well rooms

M.O. Municipality

3 Months

Garmian

540,356

2010

72

Digging of five water wells in Aghgeler

KNOC oil company

2 months

Sulaimany

589,683

2009

73

Yeki badawan main Streets

M.O. Municipality

2 years

Erbil

5,416,600

2010-2012

74

Hay askari, shahidan project

M.O. Municipality

1year

Erbil

1,250,000

2009

75

Azadi street project

M.O. Municipality

1 Year

Erbil

833,300

2009

76

Construction of Kirkuk Cement Factory Weighing 5 bases

KUK Cement Fac.

3 months

Kirkuk

545,000

2009

77

Construction of Oil fields accommodation and project camp area Sulaimany - Takya include pump station, boreholes and main pipe line.

KNOC - ZOZIK

3 months

Sulaimany

2,800,000

2009

78

implementation of the project of establishing the course of Funds (3 × 3) along the embankment of the station (2000) to the station (3100) in the city of Ainkawa

M.O. Municipality

3 months

Erbil-Ainkawa

224,500

2008

79

Supply of school appliances (tables, desks, furniture’s, electric appliances...etc.) for three

ACDI VOCA

2months

Erbil

430,000

2008

80

schools ACDI VOCA CHAR BRA, CHAR DERIA & 4b group

2months

81

Supply and construction of Zilkan pump station and GI pipe line

DAI/OTI/USAID

1 months

Nainawa-

95,000

2007

82

Construction & Paving of Hay AL kadisia Road by Asphalt in Talafer

IRD

2 months

Nainawa-

143,000

2007

83

Construction of Tal Qasab network GRP pipe line (4",2",1", 3/4")

IRD

2 months

Nainawa-

246,000

2007

84

Rebuild works for renovation of Mosul governorate agencies (schools, clinic centers, sport centers, play yard, etc.)

IRD/ USAID

12months

Mosul

3,440,000

2007 - 2008

85

implementation of the project of establishing a school containing (12) Division in the neighborhood of Sven in the city of Irbil

M. O. Education

1 Year

Erbil

1250000

2007

86

Implementation of Synthetic limbs Emergency hospital

UNOPS - Zozik Co.

1year

DOHUK

384,000

2005

87

implementation of the project of establishing a school containing (12) Division in the

M. O. Education

1 Year

Erbil

1,234,000

2007

88

neighborhood of Sven in the city of Irbil

89

Deliver electricity to the project Shrdhaohy Diana / Soran with the purchase of generating electricity

M.O. Elec.

6 months

Erbil-Soran

654000

2007

90

Construction of sports stadium Banslawa

M.O. Municipality

3 months

Erbil-

202500

2006

91

Establishment of a sports stadium Soran

M.O. Municipality

24 months

Soran

1983400

2006

92

Stage two of UNDP program of Dohuk Governorate for installation of 132/33/11 kV

UNDP -

18months

Dohuk

1,850,000

2005-2006

93

Sumail Subs. & 33/11 kV Dohuk1 and Sheladize Subs

GALALAH Co.

94

Construction of Al-Khazer subs.33/11 KV substation In Mosul Governorate. ZOZIK Co.

Washington Group.

12months

Mosul

1,450,000

2005-2006

95

Construction and erecting of 33kv transmission line (DHK - Atrush / Zakho - Darkar)

Washington Group. MITASH Turkey

12months

Dohuk

6,634,000

2005-2006

96

Construction and erecting of 33kv transmission line Al Khazer - Hamdania

Washington Group. Ozdil Turkey Co

6months

Mosul

2,600,000

2005-2006

97

implementation of the project of establishing a school containing (12) in the Division of

M. O. Education

12 months

Erbil-Soran

1220000

2004

98

implementation of a project to build a health center with a doctor's house in the area of Daman on

M. O. Health

6 months

Erbil

432100

2004

99

implementation of the project of establishing a school contains (6) Division in the village of Bntrd to Daman

M. O. Education

9 months

Erbil

342000

2004

100

implementation of the project of establishing a school contains (6) Division in the village of Mirth to spend Daman

M. O. Education

9 months

Erbil

323,700

2004

101

33/11 kv ( Kani Masi, Aqre, Bard rash, Batel, Ammadia & Sarsang one distribution substation 132 kv West Dohuk )

UNDP - ENERGOINVEST

12months

Dohuk

2002 -2003

102

Stage one of (ENRP) UNDP Program of Dohuk Governorate: Profile, Survey, and Construction Foundation & Erecting for 280 towers 33 kV in these Lines (SarSang - Ammadia / Ammadia - Sheladize / Sumail - Battel/ Ammadia - Kani Masi).

UNDP - KEC Int. Indian

18months

Dohuk

2002 -2004

103

Stage one of (ENRP) UNDP Program of Dohuk Governorate: Rehabilitation for transmission line of 132 KV for 30km

UNDP - KEC Int. Indian

6months

Dohuk

2003-2004

104

Master plan of water network Dohuk city: with SEURECA France Co. under UNOPS supervision.

UNOPS - SETEC Eng. Austrian Co.

12months

Dohuk

2003-2004

105

Master plan of Dohuk city sewerage system SEURECA France

UNOPS -

12months

Dohuk

2003-2004

106

Projects of rebuilt Iraq in North of Iraq (Salahaddin, Kirkuk, Nainawa & Dohuk Governorate) to complete more than 200 projects of renovation buildings, training courses

USAID - ZOZIK Co.

24months

Dohuk

2003-2005

107

Construction of Emergency hospital in Dohuk

UNOPS - ZOZIK Co.

18months

Dohuk

364,000

2002-2005